Purchase order follow up with suppliers, without the daily chasing.
By Irshad KK, CEO, mobai.
The short answer
Purchase order follow up with suppliers works best on a fixed calendar, not by feel. Ask for written acknowledgement within 24 hours, confirm the dispatch date at the halfway point, check readiness two days before, collect the invoice, e-way bill and LR numbers on dispatch, and escalate any PO one day late. Asking for proof at each step, not promises, is what ends the chasing.
"Dispatch tomorrow, sir." The supplier said it on the 5th, again on the 8th and again on the 11th. The trims for a knitwear order in Tiruppur finally arrived on the 14th, and the buyer's ship date didn't move.
Every purchase manager in India has heard that line. The fix is not more calls. It is a purchase order follow up with suppliers that asks for proof on fixed days, so a late PO shows up as late a week before it hurts.
What chasing suppliers really costs
Late material rarely shows up in the accounts as a cost. It shows up as an idle line, an angry customer and a buyer who spends half the day on the phone.
Example: a pump manufacturer in Coimbatore with about 40 open purchase orders at any time. These are assumptions; put in your own.
| Cost | Assumption | Per month |
|---|---|---|
| Assembly line stopped for missing parts | 3 days a month, ₹60,000 of labour and overhead per day | ₹1,80,000 |
| Emergency local buying | ₹5 lakh bought locally at 8% above the regular price | ₹40,000 |
| Buyer time spent chasing | 55 hours at ₹400 an hour | ₹22,000 |
| Total | ₹2,42,000 |
That is close to ₹29 lakh a year, before counting penalty clauses or a customer who moves to a competitor. In a trading business the same gap becomes a stockout; our post on the cost of stockouts for distributors works through that side.
The follow-up calendar: five points per PO
Set the calendar from the PO date and the lead time the supplier agreed. Every PO gets the same five touch points.
| When | What you ask for | Proof you accept | If it fails |
|---|---|---|---|
| Within 24 hours of the PO | Acknowledgement, with the committed dispatch date | Reply on WhatsApp or email with the date in writing | Call the same day; an unacknowledged PO is not an order |
| Halfway through the lead time | Is the date still good? Is raw material in? | A yes with the date repeated, or a new date | Plan for the new date now; tell production or sales |
| 2 days before dispatch | Is the material ready? | A photo of packed goods or a packing list | Ask for a part dispatch of what is ready |
| On dispatch | Invoice number, e-way bill number, transporter and LR or docket number | The numbers themselves | "Dispatched" without an LR number means not dispatched |
| On receipt | GRN against PO, quantity and quality check | Your GRN | Raise shortage or rejection within 48 hours |
A promise is not proof. Only the second-last column counts.
Ask for numbers you can check
The most useful question is the one the supplier can't answer vaguely.
- E-way bill number. For most consignments above ₹50,000, the supplier needs an e-way bill before the goods move. If they can give you the number, the goods have at least been booked to travel.
- LR or docket number. With the transporter's name, you or your team can call the transporter directly instead of waiting for the supplier.
- Packed-goods photo. Two days before dispatch, a photo of cartons with your PO number on the label tells you more than any phone call.
Message templates that get a one-line answer
Keep each message short, with the PO number, and one question.
Acknowledgement (sent with the PO):
PO 4471 attached: 2,000 m elastic, 25 mm, white. Please confirm by tomorrow the dispatch date you can commit to.
Halfway check:
PO 4471 is due for dispatch on 18 Dec. Is that date still good? Please reply with the date.
Two days before:
PO 4471 dispatches on 18 Dec. Please send a photo of the packed goods and the packing list today.
On dispatch:
Thank you. For PO 4471 please send the invoice number, e-way bill number and LR number.
Many suppliers in Tamil Nadu and Kerala will answer a voice note faster than a typed message. That is fine, as long as the answer is a date or a number, and someone writes it into the PO record.
Score your suppliers every month
Chasing gets easier when suppliers know you are measuring. The standard measure is on-time in-full (OTIF).
OTIF = PO lines received in full quantity by the committed date ÷ total PO lines due in the month
| Supplier | PO lines due | On time in full | OTIF | Action |
|---|---|---|---|---|
| Elastic, Tiruppur | 24 | 22 | 92% | Keep |
| Castings, Coimbatore | 18 | 12 | 67% | Add 5 days to planned lead time; find a second source |
| Packaging, Kochi | 30 | 27 | 90% | Keep |
Share the score with each supplier once a quarter. Most improve once they see the number, and the ones that don't tell you where to look for a backup.
When to escalate
Escalate early and by rule, not by temper.
- One day late on dispatch: the buyer calls the supplier's owner or sales head, not the dispatch clerk.
- Three days late: the purchase manager agrees a new date in writing and informs production or sales.
- Second late PO in a month from the same supplier: split the next order with another supplier.
What to do this week
- List every open PO with its committed dispatch date. If a PO has no committed date in writing, ask for one today.
- Send the halfway-check message for every PO due in the next 10 days.
- Start asking for e-way bill and LR numbers on every dispatch.
- Work out last month's OTIF for your five biggest suppliers from GRN dates.
Where an AI agent fits
The calendar above is simple. Running it for 40 or 400 open POs, every day, is where it breaks down.
The mobai. purchasing agents work on top of your existing system, whether that is Tally, SAP Business One, Odoo or Zoho. They work out what to buy and when from sales and stock, collect and compare supplier quotes, place the order after a person approves, and chase suppliers for late deliveries, so the follow-up messages go out on the right day and the answers are recorded against the PO.
What stays with people: approving purchase orders above a set amount, negotiating price, and the call to a supplier's owner when a PO is badly late. If you raise ten POs a month to two trusted suppliers, a shared sheet and a weekly review may be all you need. On the sales side, the stock agent warns when a fast-selling item is about to run out, which is often when a late PO first becomes visible. For our work with manufacturers and traders, see AI agents in India and AI agents in Tamil Nadu.
If you'd like to see what this calendar would look like on your open POs, send us your details and we'll reply the same working day.